Final Project - Updated Timeline
- Yavneeka Patel
- Mar 9, 2015
- 1 min read
Timeline
Week 3a: March 12 - 18 (SPRING BREAK)
Main Goal: Continue working on building the prototype (Module 4) and coding (Module 1)
Should be fairly close to complete by the end of fall break
Week 3b: March 19 - 25
Main Goal: Begin Module 3: speech recognition
Work on Module 3
Finish Module 1: Coding should be done at this point
Get the Jar file to run on the Galileo (I won't have access to it during break, so majority of this work has to happen this week)
Week 4: March 26 - April 1
Main Goal: Work on Module 3
Week 5: April 2 - April 8
Main Goal: Begin Module 4
Module 4: Assemble the prototype, adding in robotic components
Continue working on Module 3
Week 6: April 9 - April 15
Main Goal: Finish Module 4 and any remaining Module
Week 7: April 16 - April 22 (LAST WEEK) (HARD DEADLINE)
Main Goal: Present final project on April 23rd
Complete all unfinished modules
Recent Posts
See AllSo we've made it to the very end. Through all the ups and downs and we're all still standing. It was an amazing semester and I made some...
/** *Java Speech Grammar Format (JSGF) file *This file holds all the words that the program will recognize **/...
/* * Copyright 2013 Carnegie Mellon University. * Portions Copyright 2004 Sun Microsystems, Inc. * Portions Copyright 2004 Mitsubishi...
Comments